

In 2007, the Laguna Division Planning Group was formed to identify potential restoration projects within this reach of the river. The intent was to identify potential restoration projects and combine resources to ensure any actions taken in the area would not affect other potential restoration projects or ongoing river operations. Currently, there are three river operational requirements and constraints: water delivery, sediment removal, and power generation.
The Laguna Division Planning Group consists of representatives from the following organizations:
The product from the planning group was identified as the Laguna Division Conservation Area (LDCA), which is scheduled for restoration beginning in 2012 with a completion date of 2015. The LDCA is nestled between the Imperial Dam and the Laguna Dam with Mittry Wildlife Area to the east and the Laguna Settling Basin to the west. LDCA will replace large saltcedar stands with a mosaic of open water, marsh, riparian and upland habitat, restoring as much as 1,200 acres of native vegetation along several former river meanders. These land cover types would be maintained with a maximum base flow of 100 cfs from the Gila Settling Basin. To minimize earthwork, cuts and fills would follow the existing topography where feasible. Adjacent terraces would be graded to allow flooding and promote the establishment of native riparian species. Water control structures would be created to manage water levels. Upland vegetation will receive water through a combination of flooding and drip irrigation.
The habitat of LDCA is expected to attract a variety of LCR MSCP covered species including the California black rail, Yuma clapper rail, southwestern willow flycatcher, yellow-billed cuckoo, Yuma hispid cotton rat, and western least bittern.
A fact sheet for this Conservation Area can be found here. Technical Reports for this Conservation Area can be found here.
Updated November 28, 2011
The Laguna Division Conservation Area, located between river miles 43-49, contains Reclamation withdrawn lands in both Arizona and California. Construction activities area expected to begin late in 2011 and be completed in 2014. During the construction period, there will be no public access.
For specific information on the Conservation Area, please contact Terry Murphy, Restoration Group Manager, at (702) 293-8140 or via email at tmurphy@usbr.gov.
Click on the map below to see the Laguna Division Conservation Area using the interactive GIS map.
Each Conservation Area targets certain LCR MSCP covered and evaluation species habitats. Below, on the left, is a list of the LCR MSCP species in which habitat will be targeted for creation for in this particular conservation area. To the right is a list of LCR MSCP species that, through monitoring, have been found utilizing the conservation area.
| Targeted LCR MSCP Species | LCR MSCP Species Utilizing Site |
| Riparian Obligates | To be Determined after construction |
| Arizona Bell's Vireo | |
| Elf Owl | |
| Gila Woodpecker | |
| Gilded Flicker | |
| Sonoran Yellow Warbler | |
| Southwestern Willow Flycatcher | |
| Summer Tanager | |
| Vermilion Flycatcher | |
| Yellow-Billed Cuckoo | |
| Bats, Small Mammals, and Insects | |
| California Leaf-Nosed Bat | |
| Townsend's Big-Eared Bat | |
| Western Red Bat | |
| Western Yellow Bat | |
| Yuma Hispid Cotton Rat | |
| Marsh Birds | |
| Black Rail | |
| Least Bittern | |
| Yuma Clapper Rail |
All environmental compliance is completed for LDCA and the Section 404 permit was approved. Equipment has been mobilized to the site and construction activities began the first week of October 2011. Construction starts with placement of 2,300 ft of 48” HDPE pipeline from the inlet at the Gila Settling Basin to the LDCA headworks at the north end of the project site. The pipeline will be butt fusion welded and buried to maintain esthetics. Once pipeline installation is completed, clearing will begin on the site, starting from the north and working south. Access to the LDCA is prohibited during the construction period.
Project Milestones/Schedule
LDCA will be completed in three primary phases:
Throughout the entire project, stakeholder coordination; environmental, cultural, and lands compliance; site monitoring; and project management activities are ongoing.
The following table includes milestones and/or the schedule. Time frames listed for the project are subject to change.
| Date | Milestone |
| 2007 | Laguna Division Planning Group Formed |
| 2009 | Draft Design Developed |
| October 2010 | Project Approved for Inclusion to LCR MSCP |
| December 2010 | Draft Environmental Assessment |
| February 2011 | Final Environmental Assessment/Finding of No Significant Impact |
| February-May 2011 | Corps of Engineers Section 404 Permit Coordination |
| September-December 2011 | Pipeline Construction |
| September 2011- November 2013 | Clearing Operations and Earth Moving |
| July 2012-April 2014 | Construction of Water Control Structures, Roadways, and Trails |
| March 2014-July 2016 | Vegetation Planting |
Laguna Poster
Below is the Laguna Division Conservation Area 2011 poster. You can click on the poster for a larger view.
Laguna Construction Photos
Below are photos of construction in November 2011 from the Laguna Division Conservation Area. You can click on the images for a larger view.
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
Acreage Map
This map shows the acreage for this area. You can click on the map for a larger view.
This gallery includes photos of this conservation area. If you require larger photos, please contact our webmaster Michelle Reilly at mreilly@usbr.gov.
Below is a video on the Laguna Diversion Conservation Area program.